Text version of infographic titled "CWCB Measurement Projects: Draft Schedule"
Accommodation statement: the State of Colorado is committed to providing equitable access to our services to all Coloradans. Please contact Anna Porter (anna.porter@state.co.us or 303-866-3441 x3244) for personalized accessibility assistance. We will contact you directly within three business days. Visit our accessibility webpage for more information and services, including AIRA, our free service for blind and low-vision users. This page provides a text-only version of a visual diagram titled "Review Cycles of the State Fiscal Year."
A visual timeline titled "CWCB Measurement Structures Project: Draft Schedule (Subject to Change)" outlines four rounds of application and installation phases for water measurement structures across Colorado river basins.
Row 1:
Round 1 (2025–2026): Applications accepted from Division 6 (Yampa, White, & Green River Basins) and Division 7 (San Juan & Dolores River Basins).
Round 2 (2026–2027): Applications accepted from Division 4 (Gunnison River Basin) and Division 5 (Colorado River Basin).
Round 3 (2027–2028): Contingent on applicant interest from Rounds 1 and 2.
Round 4 (2028–2029): Also contingent on prior interest. All installations must be completed by September 2029.
The schedule is subject to change based on applicant interest and project logistics.
Row 2:
Row 2 outlines the key phases of Round 1 of the CWCB Measurement Structures Project for Division 6 (Yampa, White, and Green River Basins) and Division 7 (San Juan and Dolores River Basins). Each phase is visually separated and color-coded in shades of purple and white, representing the progression of activities over time. The timeline includes five sequential phases:
- Program Kick-off – September 2025
- Basin Information Meetings – Fall 2025 (for Divisions 6 & 7)
- Application Submissions – Fall 2025 (for Divisions 6 & 7)
- NEPA Process for Accepted Applications – Winter 2025–2026
- Installations – Spring to Fall 2026 (for Divisions 6 & 7)
Row 3:
Row 3 outlines the key phases of Round 2 of the CWCB Measurement Structures Project for Division 4 (Gunnison River Basin) and Division 5 (Colorado River Basin). Each phase is visually separated and shaded from dark blue to light blue, representing the progression of activities over time. The timeline includes four sequential phases:
- Basin Information Meetings – Summer 2026 (for Divisions 4 & 5)
- Application Submissions – Fall 2026 (for Divisions 4 & 5)
- NEPA Process for Accepted Applications – Winter 2026–2027
- Installations – Spring to Fall 2027 (for Divisions 4 & 5)